Bancroft council has approved a $4.67 million contract with Beacon Construction Ltd. for the construction of a new water tower.
The decision was made at Friday’s special meeting of council.
Deputy Mayor Wayne Wiggins moved the motion, seconded by Coun. Charles Mullett.
The town’s current water tower, located on Newkirk Boulevard, was built back in 1984 and has reached the end of its lifespan.
The water tower replacement project has gone through two years of approval processes.
A provincial grant request was initially denied but the following year, in 2026, the application was reconsidered and was successful.
This summer, the provincial government committed $3.65 million to replacing the tower through the Housing-Enabling Water Systems Fund.
The contract includes funding for the construction of a new new standpipe, a new control building and valve chamber, upgrading watermain and Snow Road isolation valves and decommissioning the current tower (once the new tower becomes operational).
Kaitlyn Nagora, an engineer with p2g Consultants, presented recommendations outlined in the tender review report.
Mayor Paul Jenkins confirmed the community plan has allotted funding for the estimated cost of the water tower.
Infrastructure Manager, Public Works Jake Krupa told council the cost of construction is under budget.
Nagora said the new water tower would meet capacity and projected capacity for the town’s population in accordance with the community plan.
Coun. George Eastman inquired about the life expectancy of the new tower.
Krupa responded that the new tower would require less maintenance in comparison to the current structure. It will not need to be sandblasted or painted over time,